Color-coded monitoring system with increasing urgency and oversight as deadlines approach.
Green (>60 Days to Deadline)
Status: Routine monitoring, no escalation required.
Actions:
- Weekly status check: Project manager reviews progress
- Milestone tracking: Ensure surveyor, municipal clerk, land registry office on schedule
- No escalation: Standard project management
Example:
- Approval date: March 15, 2025
- Current date: April 1, 2025 (77 days to deadline)
- Status: Green - plan preparation in progress, surveyor on schedule
Yellow (30-60 Days to Deadline)
Status: Moderate concern, weekly status checks required.
Actions:
- Weekly status meetings: Project manager + surveyor + municipal clerk
- Identify risks: Any delays in plan preparation, corrections needed?
- Executive notification: Update senior management (director level) on timeline status
- No critical actions yet: Still time to resolve issues
Example:
- Approval date: March 15, 2025
- Current date: May 1, 2025 (43 days to deadline)
- Status: Yellow - plan submitted to land registry office, awaiting appointment
- Action: Weekly check-ins with land registry office, confirm appointment scheduled
Orange (15-30 Days to Deadline)
Status: Significant concern, daily monitoring, executive escalation.
Actions:
- Daily status checks: Project manager contacts surveyor, municipal clerk, land registry office daily
- Executive escalation: VP/CAO briefed on timeline risk
- Mitigation planning: Develop contingency plans
- Option 1: Expedite land registry appointment (senior staff contacts registry office manager)
- Option 2: Prepare second approval application (if first will expire)
- Communication: Notify council, approving authority of timeline risk
Example:
- Approval date: March 15, 2025
- Current date: May 28, 2025 (16 days to deadline)
- Status: Orange - land registry office backlog, no appointment yet
- Action: CAO contacts Land Registrar directly, requests priority appointment
- Result: Appointment scheduled for June 6 (7 days before deadline)
Red (7-15 Days to Deadline)
Status: Critical, crisis mode, all-hands coordination.
Actions:
- Twice-daily updates: Morning and afternoon status calls
- Executive involvement: CAO/CEO directly manages timeline
- All-hands: Cancel other meetings, prioritize expropriation plan registration
- Contingencies activated:
- Expedited approval: Contact approving authority, request expedited second approval if needed
- Legal review: Solicitor reviews plan for any defects (correct before registration)
- Land registry: Senior management contacts Land Registrar for emergency appointment
- Council briefing: Inform council of timeline risk, prepare for potential approval expiry
Example:
- Approval date: March 15, 2025
- Current date: June 6, 2025 (7 days to deadline)
- Status: Red - land registry appointment on June 6, but plan has minor defects
- Action:
- Morning: Solicitor reviews plan, identifies corrections needed
- Afternoon: Surveyor makes corrections (priority work)
- Evening: Corrected plan submitted to municipal clerk
- Next morning: Municipal clerk approves, plan ready for registration
- June 6 PM: Plan registered at land registry office (7 days before deadline)
Critical (<7 Days to Deadline)
Status: Emergency, weekend work, highest executive priority.
Actions:
- Emergency procedures: Weekend work authorized, overtime approved
- CEO/Mayor involvement: Highest political/administrative level engaged
- Legal escalation: External counsel engaged if needed
- Parallel tracks:
- Track 1: Register current plan (even if minor defects)
- Track 2: Apply for second approval (if Track 1 fails)
- Communication: Daily briefings to council, approving authority
- Post-mortem: After deadline met (or missed), conduct lessons-learned review
Example:
- Approval date: March 15, 2025
- Current date: June 11, 2025 (2 days to deadline)
- Status: Critical - land registry office appointment on June 13 (last possible day)
- Action:
- June 11: CEO contacts Land Registrar, confirms appointment for 9 AM June 13
- June 12: Legal team pre-registers plan documents, ensures no issues
- June 13, 9 AM: Municipal clerk attends land registry office in person
- June 13, 10 AM: Plan registered (3 hours before 4 PM deadline)
- Post-mortem: Review why timeline became critical, implement process improvements
---
This skill activates when you:
- Track expropriation statutory deadlines (3-month registration, Form 2/7 service)
- Calculate deadline expiry dates accounting for weekends and holidays
- Coordinate plan preparation with surveyors and municipal clerks
- Escalate timeline risks using color-coded protocols (green, yellow, orange, red, critical)
- Manage emergency situations when deadlines at imminent risk
- Conduct post-project reviews to improve deadline management processes