🎯

expropriation-statutory-deadline-tracking

🎯Skill

from reggiechan74/vp-real-estate

VibeIndex|
What it does

expropriation-statutory-deadline-tracking skill from reggiechan74/vp-real-estate

πŸ“¦

Part of

reggiechan74/vp-real-estate(53 items)

expropriation-statutory-deadline-tracking

Installation

npm installInstall npm package
npm install -g @anthropic-ai/claude-code
git cloneClone repository
git clone https://github.com/reggiechan74/vp-real-estate.git
pip installInstall Python package
pip install numpy pandas scipy
pip installInstall Python package
pip install 'markitdown[docx]' # document conversion
pip installInstall Python package
pip install openpyxl # Excel export for MLS extraction

+ 2 more commands

πŸ“– Extracted from docs: reggiechan74/vp-real-estate
4Installs
5
-
Last UpdatedJan 15, 2026

Skill Details

SKILL.md

Expert in managing critical statutory timelines under Ontario Expropriations Act including 3-month registration window, Form 2/7 service timing, and escalation protocols by timeline urgency. Use when tracking expropriation deadlines, calculating notice periods, or managing timeline-critical acquisitions. Key terms include statutory deadlines, 3-month registration, Form 2 service, Form 7 notice, approval expiry, escalation protocols

Overview

You are an expert in tracking and managing statutory deadlines under the Ontario Expropriations Act, ensuring procedural compliance and avoiding approval expiry through systematic monitoring and escalation.

Granular Focus

Managing critical statutory timelines (subset of Stevi's capabilities). This skill provides operational deadline tracking - NOT legal interpretation of expropriation law.

Ontario Expropriations Act Deadlines

Key statutory windows that cannot be extended and result in approval expiry if missed.

3-Month Registration Window (s.9)

Statute: Expropriation plan must be registered within 3 months of approval.

s.9(2): "Where an expropriation plan is not registered within three months after the approval becomes final, the approval expires and is of no effect."

Countdown calculation:

  • Approval date: Date approving authority signs approval certificate (not application date)
  • Expiry date: Approval date + 90 days (calendar days, not business days)
  • Critical: If day 90 falls on weekend/holiday, deadline does NOT extend - must register before weekend

Example:

  • Approval date: March 15, 2025 (Saturday)
  • Expiry date: March 15 + 90 days = June 13, 2025 (Friday)
  • Registration deadline: June 13, 2025 by 4:00 PM (Land Registry Office closing time)
  • No extension: If June 13 falls on a holiday (e.g., Good Friday), deadline is June 12 (previous business day)

Calculation methodology:

  • Use calendar calculator (Excel, Google Sheets, project management software)
  • Formula: =DATE(approval_year, approval_month, approval_day) + 90
  • Verify manually (count days on calendar to avoid software errors)
  • Contingency: Calculate as 85 days (5-day buffer for unforeseen issues)

Municipal clerk coordination:

  • Expropriation plan preparation: Surveyor prepares plan (2-4 weeks)
  • Plan review: Municipal clerk reviews plan for compliance with O.Reg. 363/90 Form 6 requirements (1 week)
  • Corrections: If plan defects identified, surveyor corrects and resubmits (1-2 weeks)
  • Final approval: Municipal solicitor approves plan for registration (1 week)
  • Total: 5-8 weeks from approval to plan ready for registration

Timeline example:

  • Week 0 (March 15): Approval received
  • Weeks 1-3: Surveyor prepares expropriation plan
  • Week 4: Municipal clerk reviews plan - identifies error (property description inconsistent with legal description)
  • Week 5: Surveyor corrects plan, resubmits
  • Week 6: Municipal solicitor reviews and approves
  • Weeks 7-9: Wait for land registry office appointment (backlog)
  • Week 10 (May 24): Plan registered - 65 days after approval (25-day buffer remaining)

Contingency planning if deadline at risk:

  • Option 1: Obtain second approval (re-apply if first approval will expire)

- Risk: Approving authority may deny second application

  • Option 2: Register plan with minor defects, correct via amendment

- Risk: Registry office may reject plan

  • Option 3: Abandon expropriation, re-apply after approval expires

- Cost: Delay, additional approval fees, political risk

Form 2 Service Timing

Best practice: Serve Form 2 (Notice of Application for Approval) 30 days before plan registration.

Not statutory requirement, but:

  • Natural justice: Owners should have notice of expropriation before plan registered
  • Reduces challenges: Serving Form 2 post-registration invites procedural challenges
  • Practical: Allows owners to contact authority, ask questions, prepare

Service method requirements (s.11):

  • Personal service: Deliver Form 2 directly to owner (preferred method)
  • Registered mail: Mail to owner's address (requires 5 days delivery time)
  • Substituted service: If owner cannot be located, court order for alternative service (post on property, publish in newspaper)

Timing calculation:

  • Registration date: June 13, 2025
  • Form 2 service: 30 days prior = May 14, 2025
  • Service method: Personal service (same day) or registered mail (allow 5 days delivery = serve by May 9)

Proof of service documentation:

  • Affidavit of service: Sworn statement by process server confirming date/time/method of service
  • Registered mail receipt: Canada Post tracking showing delivery date
  • Keep records: File affidavits with municipal clerk (proof of compliance)

Form 7 Notice (30 Days Minimum)

Statute: Form 7 (Notice of Expropriation) must be served at least 30 days before possession (s.11).

s.11(1): "At least thirty days before the date fixed for taking possession, the expropriating authority shall serve notice of the expropriation on the owner of the land."

Calculation:

  • Possession date: July 15, 2025 (date authority takes possession)
  • Form 7 service: 30 days prior = June 15, 2025 or earlier
  • Service method: Personal service or registered mail (allow 5 days delivery = serve by June 10)

Payment timing coordination:

  • Best practice: Pay compensation before or concurrent with Form 7 service
  • Statute (s.14): Compensation payable "on the date of registration" (but can be paid later if negotiated)
  • Practical: Paying at Form 7 service demonstrates good faith, reduces opposition

Possession timing:

  • Standard: 30 days after Form 7 service (minimum statutory period)
  • Extended: Can give owners more time (e.g., 60-90 days) if requested and project schedule allows
  • Example: Form 7 served June 15 states possession date of September 1 (75 days) - accommodates owner's request to relocate during summer

Escalation Protocols by Timeline

Color-coded monitoring system with increasing urgency and oversight as deadlines approach.

Green (>60 Days to Deadline)

Status: Routine monitoring, no escalation required.

Actions:

  • Weekly status check: Project manager reviews progress
  • Milestone tracking: Ensure surveyor, municipal clerk, land registry office on schedule
  • No escalation: Standard project management

Example:

  • Approval date: March 15, 2025
  • Current date: April 1, 2025 (77 days to deadline)
  • Status: Green - plan preparation in progress, surveyor on schedule

Yellow (30-60 Days to Deadline)

Status: Moderate concern, weekly status checks required.

Actions:

  • Weekly status meetings: Project manager + surveyor + municipal clerk
  • Identify risks: Any delays in plan preparation, corrections needed?
  • Executive notification: Update senior management (director level) on timeline status
  • No critical actions yet: Still time to resolve issues

Example:

  • Approval date: March 15, 2025
  • Current date: May 1, 2025 (43 days to deadline)
  • Status: Yellow - plan submitted to land registry office, awaiting appointment
  • Action: Weekly check-ins with land registry office, confirm appointment scheduled

Orange (15-30 Days to Deadline)

Status: Significant concern, daily monitoring, executive escalation.

Actions:

  • Daily status checks: Project manager contacts surveyor, municipal clerk, land registry office daily
  • Executive escalation: VP/CAO briefed on timeline risk
  • Mitigation planning: Develop contingency plans

- Option 1: Expedite land registry appointment (senior staff contacts registry office manager)

- Option 2: Prepare second approval application (if first will expire)

  • Communication: Notify council, approving authority of timeline risk

Example:

  • Approval date: March 15, 2025
  • Current date: May 28, 2025 (16 days to deadline)
  • Status: Orange - land registry office backlog, no appointment yet
  • Action: CAO contacts Land Registrar directly, requests priority appointment
  • Result: Appointment scheduled for June 6 (7 days before deadline)

Red (7-15 Days to Deadline)

Status: Critical, crisis mode, all-hands coordination.

Actions:

  • Twice-daily updates: Morning and afternoon status calls
  • Executive involvement: CAO/CEO directly manages timeline
  • All-hands: Cancel other meetings, prioritize expropriation plan registration
  • Contingencies activated:

- Expedited approval: Contact approving authority, request expedited second approval if needed

- Legal review: Solicitor reviews plan for any defects (correct before registration)

- Land registry: Senior management contacts Land Registrar for emergency appointment

  • Council briefing: Inform council of timeline risk, prepare for potential approval expiry

Example:

  • Approval date: March 15, 2025
  • Current date: June 6, 2025 (7 days to deadline)
  • Status: Red - land registry appointment on June 6, but plan has minor defects
  • Action:

- Morning: Solicitor reviews plan, identifies corrections needed

- Afternoon: Surveyor makes corrections (priority work)

- Evening: Corrected plan submitted to municipal clerk

- Next morning: Municipal clerk approves, plan ready for registration

- June 6 PM: Plan registered at land registry office (7 days before deadline)

Critical (<7 Days to Deadline)

Status: Emergency, weekend work, highest executive priority.

Actions:

  • Emergency procedures: Weekend work authorized, overtime approved
  • CEO/Mayor involvement: Highest political/administrative level engaged
  • Legal escalation: External counsel engaged if needed
  • Parallel tracks:

- Track 1: Register current plan (even if minor defects)

- Track 2: Apply for second approval (if Track 1 fails)

  • Communication: Daily briefings to council, approving authority
  • Post-mortem: After deadline met (or missed), conduct lessons-learned review

Example:

  • Approval date: March 15, 2025
  • Current date: June 11, 2025 (2 days to deadline)
  • Status: Critical - land registry office appointment on June 13 (last possible day)
  • Action:

- June 11: CEO contacts Land Registrar, confirms appointment for 9 AM June 13

- June 12: Legal team pre-registers plan documents, ensures no issues

- June 13, 9 AM: Municipal clerk attends land registry office in person

- June 13, 10 AM: Plan registered (3 hours before 4 PM deadline)

- Post-mortem: Review why timeline became critical, implement process improvements

---

This skill activates when you:

  • Track expropriation statutory deadlines (3-month registration, Form 2/7 service)
  • Calculate deadline expiry dates accounting for weekends and holidays
  • Coordinate plan preparation with surveyors and municipal clerks
  • Escalate timeline risks using color-coded protocols (green, yellow, orange, red, critical)
  • Manage emergency situations when deadlines at imminent risk
  • Conduct post-project reviews to improve deadline management processes